RGCS  (Rural Growth Centres)

About UsHome

INTRODUCTION

The Sarawak Government commisioned a feasibility study on the establishment of Rural Growth Centres (RGC) in the State in January 1994 and 9 areas were selected. Planning for this study were essentially to facilitate and accelerate the socio-economic growth and betterment of the quality of life in the rural areas.

In order to address these issues, the State Government has decided to develop the rural areas of Sarawak in a more systematic, coordinated and integrated manner through RGC Development Approach. Through this means it is envisaged that the rural sector of Sarawak will be able to compete with the urban centres.

The Rural Growth Centre Programme, therefore has been formulated to transform the rural areas into attractive places to live and work in. Inevitably this programme will assist to speed up rural development as well as to eradicate poverty.

Click to see more options
Objectives of R.G.C.

Socio-economic Characteristics

Details of current and projected population, labour force, employment and migration in the RGCsare presented in Table 1.1. Average annual population growth is anticipated to vary between 1.7% - 2.4%. In regard to the labour force, an increase in the Labour Force Participation Rate (LFPR) is expected in most centres particularly the LFPR for females) and by the year 2012, Beladin would have the largest labour force of 4,891 and Nanga Spak, with 1,403 the smallestlabour force.

Migration in all RGCs is expected to continue in the short-run but a secular decline in the rate is forecast. Estimated rates of migration which currently vary from 3.6% to 30.4%, are projected to fall to levels ranging from 0.1% to 0.8%.

Details of current and projected monthly household incomes in the RGCs are shown in Table 1.1.

Click to See Table 1.1. Click to close this document

DEVELOPMENT PROPOSALS

The integrated, multi-component RGC Development Plan specifically identified a wide range of project proposals with the objective of addressing poverty and raising the quality of life in the RGCs. The project proposals can be subsumed under four main development components:-

No.
Components
No. of Projects
Estimated Cost (RM) 
I
    Infrastructure
134
367.3 million 
II
    Economic Development
156
91.76 million 
III
    Service Centre
239
33.0 million 
IV
    Human Resource Development (HRD)     Proposals
4
10.74 million 

MAJOR DEVELOPMENT CONSTRAINTS

PROJECT JUSTIFICATION

      The Projects are proposed based on the following justifications:-


DEVELOPMENT COSTS

The total development cost of the Project is estimated at RM502.8 million (US132.32 million) of which Infrastructure components account for 73.05%, Economic Base/productive sector 19.25%, Service Centre 6.57% and Human Resource Development proposals 2.14% respectively.

FINANCIAL/ECONOMIC ANALYSIS

Financial internal rates of return (FIRR) and Economic internal rates of return (EIRR) have been estimated for economic base/productive sector projects the RGCs. The combined FIRR and EIRR for the RGCs were as follows:-

 
  RGC  
GEDONG BALINGIAN BELADIN SUNDAR   
AWAT-AWAT
OVERALL  
%
FIRR (%)  
EIRR (%)
17.2  
20.1
16.2  
17.1
20.8  
22.4
33.8  
53.9
18.3  
21.1 
 
Overall the FIRR and EIRR exceeded the OCC (Opportunity Cost of Capital) assumed to be 10%.

** Note:  The figure for other RGCs areas are not included.

PROPOSED ORGANISATION AND MANAGEMENT  STRUCTURE

Existing state and/or federal institutions are recommended as executing agencies for their specific parts of the RGC Development Plan but overall planning of the RGC should be the responsibility of the State Planning Unit (SPU). Planning Coordination, Monitoring and Evaluation at the RGC level, however, is recommended to be undertaken by a Project Management Unit (PMU). The PMU would carry out interagency coordination and synchronisation of the needed activities making up the projects components to ensure effective implementation and carry out the long-term monitoring and evaluation.

Click to view Organisation Structure

PROPOSED IMPLEMENTATION SCHEDULE










 


Sub-packaging is also included in the proposals to facilitate sequential, phased implementations and allows the capacities of facilities to be gradually expanded, upgraded or modified in parallel with the pace of population build-up in the RGCs.

The recommended proposals are the followings:-
 
Phase I
Sundar/Awat-Awat  
Gedong  
Semop (previously Belawai)  
Beladin
Phase II Long Lama  
Padawan Complex  
Nanga Spak  
Balingian
The specific development proposals are recommended to be categorised into three packages as per table below:-
Package Duration 
Package I 1994 - 1995 
Package II 1996 - 2000 
Package III 2001 - 2012 

RURAL GROWTH CENTERS : Maps     

Click on the links below for RGC Maps :